Alexandra Park 'months behind' after building issues hit apartment project

The 246-unit Alexandra Park apartment project in Auckland is far from finished, after construction woes struck at the Greenlane site.

In video filmed this morning, the Herald showed how the towers on the Greenlane Rd site are up but work is far from complete.

A number of tower cranes are still hoisting goods to the structures beside the ASB Showgrounds.

Construction on the Alexandra Park apartment complex, far from finished. Photo/Dean Purcell

One source said the project was "months behind its original schedule".

One couple who had sold their large family home had hoped to move in by now. But instead they are in temporary accommodation, the source said.

They were moving to an apartment because they thought it would be lower-maintenance than their big family home.

Canam Construction walked off the site at the end of last week, claiming it was owed money. Loukas Petrou, managing director, said yesterday the builder had stopped all work.

"It is a complex situation," Petrou said.

Dominique Dowding, Alexandra Park chief executive, yesterday confirmed the builder's departure but did not respond to questions about how late the project was in delivery.

"Basically, we have replaced the contractor on the East Gate site, Canam Construction," Dowding said.

Apartments rising beside the trotting track. Photo/Dean Purcell

"We now have a new contractor in place, CMP. We believe the project and construction are in good hands and it will be completed as we wanted."

The car parking areas around Alexandra Park are to become a new urban village, as shown in these plans.

Canam was building between 112 and 118 units at the site near the ASB Showgrounds.

Stage one of the project is planned to build 246 "high-end apartments" and gross sales by last February had reached nearly $300m, Alexandra Park said last year.

Trots with a view: plans for a new Alexandra Park apartment, under construction.

The Auckland Trotting Club confirmed that it had terminated Canam's contract to build the East Gate or Building A within the 223 Green Lane West development.

"This is not a decision we have taken lightly. We have undertaken extensive negotiations with Canam to resolve issues relating to the construction contract, but no resolution has been found," the club said.

Dominique Dowding at Alexandra Park in 2015. Photo/Chris Loufte

"This is one of the largest brownfield developments currently happening in Auckland. We are committed to delivering this exceptional development as quickly as possible for our committed residents, retailers and wider community," it said.

The club said it had full confidence in the delivery of the project.

The project is near the Manukau Rd intersection. Photo/Dean Purcell

A special meeting was held with buyers last night.

Plans for the new village beside the trotting track at Greenlane.

"While some detail relating to the termination of Canam's construction contract was not able to be divulged due to legal privilege, residents were informed of all matters pertaining to their investment in Building A, and the board is satisfied with the outcome," the club said.

"Auckland Trotting Club wishes to make it clear, contrary to any allegations, that it has complied with its payment obligations under its contract with Canam," the statement said.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.