Six RTPS units shut as demand for power falls

Raichur Thermal Power Station (RTPS) has shut six of its eight power generation stations for the last 20 days at Shaktinagar in Raichur district because of the dip in demand for power in the State.

RTPS has eight units, with a total capacity of 1,720 MW. Units 1 to 7 generate a total of 1,470 MW (210x7) of power, while unit 8 generates 250 MW of power.

Units 3 and 6, which are presently being operated, generated 302 MW of power on Sunday. Wind and solar power production has caused low demand at RTPS. On Saturday, there was a demand for around 187 million units from all forms of power generation units; of this, RTPS generated eight million units from its share and supplied it.

An engineer of the electrical division of RTPS told The Hindu that the shutdown of various units was due to the reduction in demand for power, mainly on account of the onset of monsoon as well as the COVID-19 situation, which has resulted in the closure of several commercial and industrial units.

Also, this is the season when wind power reaches its peak in terms of generation, and hence the base load of thermal generation is reduced, he said.

Normally, thermal units are shut and annual maintenance taken up during this season as the pressure on them for power generation is very low. However, this time COVID-19 has further reduced the pressure on them. Various thermal units across the country too have reduced power generation.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.