Report into cost overruns of new National Children's Hospital criticises board for missing 'red flags'

A report into the cost overruns at the new National Children’s Hospital on Tuesday criticised the hospital board for missing “red flags”.

An independent inquiry by PWC, which was set up to assess the spiralling costs, found significant failures happened during the crucial planning and budgeting stages of the project.

It further warned that the cost of the new hospital could rise above €1.7billion.

The hospital, being constructed on a 12-acre site at the St James’s Hospital campus in Dublin, has been marred in controversy over spiralling costs for a number of months.

Site of the new National Children's Hospital in Dublin (RTE)

Construction firm behind National Children’s Hospital offers to pull out of project following Taoiseach's comments  

The report stated: “The basis of the original budget was flawed and risks were understated in the business case.

“There was a lack of sufficiently comprehensive or robust planning for the process to establish a Guaranteed Maximum Price (GMP) for the construction of the New Children’s Hospital.

“This created a situation in which the approved project could never be delivered within the financial parameters agreed.

“As a consequence the budget significantly underestimated the likely outturn cost. Furthermore, red flags indicating the inadequacy of the budget were missed.”

One of its many recommendations is to overhaul the project control environment to bring it up to the level of “maturity and sophistication” needed for a project of of this scale and complexity.

An artist’s impression of the new national children’s hospital (PA)

Government redirects €100m to tackle National Children's Hospital overspend  

It has advised to develop comprehensive plans to mitigate further risks, adding that if it is not effectively managed, it could lead to further cost rises.

The report further recommended: “The commercial capability and capacity of the NPH (National Paediatric Hospital) executive should be strengthened so that it is more self-sufficient and less reliant on external advisers.

“The Executive of the NPH should be strengthened in the short term to support the planning and execution of the next phase.

“The scope and responsibilities of the advisory firms that constitute the Design Team should be reviewed to reflect their future roles.

“In view of the potential consequential programme risks, a scrutiny process that includes all levels of the governance structure should be put in place.”

The Taoiseach on Tuesday said the report made for “grim reading”.

“The report finds the escalating costs of the new National Children’s Hospital related largely to an underestimation of the cost of building it in the first place, as well as the cost of delays, higher building standards and the knock-on effect of VAT.

Department of Health official was made aware of €400m cost overrun of National Children's Hospital before Budget 2019, Dail told  

“It does not recommend retendering as a feasible option and suggests there is little scope for savings.

“Our priority now must be to finish the job on time to meet the 2023 opening date, contain further cost increases and learn from the mistakes made in advance of other major projects like Metro and the National Broadband Plan.”

Stephen Donnelly, Fianna Fail health spokesman, said the report shows the cost could go beyond the current €1.73billion estimation.

He added: “We were told by the Government that the two-stage construction process was chosen because it provided a Guaranteed Maximum Price.

“The PWC review has made it clear in its findings that the so-called ‘guaranteed’ price doesn’t actually provide a contractual ceiling on cost.

“In fact it’s worse than that. We’ve learnt that there are risks of the price rising even higher, potentially another 300 million euro more.”

People Before Profit TD Brid Smith said: “Spending delays and re-profiling of funds are cuts by another name.

“The Government have now admitted that they are cutting projects like roads, the carbon fund and flood defences to pay for the cost overruns at the National Children’s Hospital.”

Budget 2019 - The key points
Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.