Plans to install electric vehicle charging points in South Lanarkshire scaled back

Plans to install 110 new electric vehicle (EV) charging points across South Lanarkshire have been scaled back.

Just 64 charging points will now be installed across 19 hubs as part of Project PACE following technical and financial limitations.

Head of roads and transportation Gordon Mackay said “despite COVID-related delays” the project was due to be completed by April.

Project PACE - a partnership between North and South Lanarkshire councils, Transport Scotland and Scottish Power Energy Networks (SPEN) – is a £5.3million project that was due to see more than 200 new charging points installed across North and South Lanarkshire by December 2020.

However, capacity issues with the SPEN energy network along with additional costs uncovered after “more detailed investigations” have forced the project to be scaled back.

Plans to install a new hub at Lanark Loch have been scrapped due to the excessive cost of connecting the car park to the grid.

In South Lanarkshire, there will be 19 new EV charging hubs with schemes in Carluke, Carnwath, Carstairs, East Kilbride, Rutherglen and Strathaven already completed.

Other hubs in Abington, Cambuslang, Crawford, East Kilbride, Forth, Hamilton, Lanark, Larkhall and Strathaven are expected to be completed in the spring.

Plans to find an alternative site to Lanark Loch are also being explored, with Lanark Lifestyles thought to be the frontrunner while funding for an extra 18 charging points from a separate Transport Scotland fund has also been secured.

A new site in Blantyre is also being assessed.

Addressing councillors on the community and enterprise committee on Tuesday, February 17, Mr Mackay said: “The transport sector is the biggest contributor to carbon emissions in Scotland.

“Despite COVID-related delays, we expect to complete the installation programme in spring of this year.

“Prior to this project starting, we had 44 public-facing charging units. This programme will increase to 108 such units and we have a further 18 units in the pipe line via a separate funding scheme.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.