HS2 boss explains why costs have spiralled by a ‘terrible’ £60bn

  • The HS2 rail project's budget has doubled, with the estimated cost now ranging from £87.7 billion to £102.7 billion in 2025 prices, nearly £60 billion more than initially projected.
  • The target opening schedule for HS2 has been delayed by 13 years, now expected between May 2036 and October 2039.
  • HS2 chief executive Mark Wild called the cost increase "terrible news," attributing it to "immaturity of design" when work started, but expressed confidence in the new robust estimates.
  • Transport secretary Heidi Alexander announced that trains will run slower than planned, at a maximum of 320kmh (199mph), and blamed "failures of successive Conservative governments" for the "obscene increase in time and costs."
  • Wild warned that canceling the project could cost between £33 billion and £58 billion, while a former Tory minister, Sir Gavin Williamson, called for the "busted project" to be brought to a close.

IN FULL

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.