Covid derails West Lothian Council plans for more affordable housing

Plans to deliver 3000 affordable homes with West Lothian within 10 years have been hit by covid.

But despite the impact of the covid pandemic, housing officials believe that the target can be met by 2023 - roughly a year behind schedule.

A report to the council’s Services for the Community Policy Development and Scrutiny Panel (PDSP) this month said that by March next year, the ten year deadline, the target will be 89% complete, including projects completed or under way.

And they believe the remaining 11 per cent could be completed by summer 2023.

Most of the affordable homes will be new builds, although the council has augmented its programme, especially in towns such as Armadale, with buybacks of former council properties.

Proposed housing sites in Armadale- including Nelson Park now earmarked as forested parkland as part of the Queen’s Platinum Jubilee Green Canopy - failed to get off the drawing board.

The report to PDSP by Development Manager, Grant Walker said that since the start of 2012/13, 2,308 affordable homes have been delivered, and a further 516 are currently under construction.

A further 253 homes are planned for site start during 2021/22 including a number of sites for new build council housing, developments by Registered Social Landlords and buybacks.

Mr Walker said: “Whilst the 3,000 units are expected to either be completed, under construction or have contracts awarded, the impact of the Covid-19 pandemic and subsequent supplies and resources issues has affected the time scales for affordable housing delivery throughout Scotland.

“It is estimated that the impact across all programmes of work is likely to be twelve months or more due to a range of issues, namely the initial lockdown of sites, furloughed staff and ongoing issues with supply of materials and labour to site operations.”

Sites scheduled to start in the next 12 months will see new homes being built on the site of the former swimming pool in Mid Street,and Marjoribanks Street in Bathgate - a total of 11 homes.

Plans for another 59 homes at a site in Wester Inch could also add to the Bathgate total.

In Livingston, construction will start on around 40 affordable homes at the Wellhead site in Murieston.

Don't miss the latest news from the West Lothian Courier. Sign up to our free newsletter here

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.