Get all your news in one place.
100's of premium titles.
One app.
Start reading
inkl
inkl

Carlyon Ward on the Contract Mistakes That Blow Up Construction Projects

Most construction disputes don’t start on-site. They start in the contract.

That’s the pattern Carlyon Ward keeps seeing across commercial construction work in Australia: projects that were commercially sound, professionally managed and competently delivered but that fell apart because the paperwork wasn’t up to scratch.

The issue in most disputes isn’t performance. It’s drafting.

Here’s where contracts go wrong, and what Commercial Lawyer Carlyon Ward says you should do about it.

1. The Scope of Works Is the Most Dangerous Document in Your Contract

It’s also the one that gets the least legal scrutiny.

A poorly drafted scope of works is the single most common and most costly mistake in Australian construction contracts. The scope defines exactly what a contractor is required to deliver, and just as importantly, what is excluded.

Without clarity on both sides of that line, disputes are almost inevitable.

In his experience advising on disputes involving multi-million dollar projects across NSW and Queensland, clients pour energy into the commercial negotiation and pay far less attention to the legal integrity of the scope itself. That’s where the exposure sits.

A contract can have strong payment terms, well-structured milestones and sensible risk allocation and still collapse the moment there’s a disagreement about what the contractor was actually supposed to build.

2. Vague Language and Loose Tender Documents Are Ticking Time Bombs

Phrases like “standard finish” or “fit for purpose” are deeply problematic unless they’re tied to defined, measurable standards.

What reads as common sense in a commercial conversation becomes a source of irreconcilable disagreement once a dispute arises.

Having worked across multiple jurisdictions, Carlyon regularly sees the same drafting failures repeat themselves:

  • Tender responses that were never properly incorporated into the final contract.
  • Inconsistencies between the tender and the executed agreement that were never resolved.
  • Verbal agreements reached on site “we’ll sort out the details later” that nobody wrote down.

Courts will not assume those gaps were filled. Every document that forms part of the contractual arrangement needs to be identified, ranked in priority and checked for inconsistency before signing.

3. Missing Variation Mechanisms Leave Every Change Open to Dispute

If the scope is the foundation, the variation clause is the load-bearing wall.

Even the best-drafted scope of works will evolve over the life of a project. That’s not a failure of planning it’s the reality of construction.

The problem arises when the contract doesn’t clearly set out how variations are requested, priced, approved and documented.

Without a functioning variation mechanism, every change becomes a potential battleground:

  • Contractors carry out additional work assuming they’ll be paid for it.
  • Principals assume it was already covered by the original scope.
  • Neither side can point to a process that was followed because none was specified.

The result is a disputed final account, a damaged commercial relationship, and too often, litigation.

Carlyon Wards advice is straightforward: the variation clause deserves as much attention as the payment clause. If the mechanism is absent, vague or impractical, fix it before the contract is executed.

4. Liquidated Damages Clauses Can Wipe Out Profit Margins If Left Unchecked

Liquidated damages or LDs are one of the most misunderstood provisions in construction contracts.

In principle, they offer certainty: a pre-agreed rate of loss applied if the contractor fails to complete on time. In practice, they’re frequently drafted in ways that expose contractors to liability far beyond what any court would consider reasonable.

From a legal perspective, three things matter:

  • LDs must represent a genuine pre-estimate of loss, not a disguised penalty.
  • Caps on liability must be reviewed and negotiated, not accepted at face value.
  • Delay notice requirements and claims procedures must be realistic and workable in practice not just technically compliant on paper.

A liquidated damages clause that was never seriously interrogated at drafting can, in a bad project, erase an entire profit margin.

This isn’t a provision to accept without scrutiny.

5. Courts Interpret Ambiguous Contracts — Usually Not in Your Favour

When a scope of works is unclear, a court won’t simply leave the matter unresolved.

Under Australian law, a judge may imply industry-standard terms, prefer the commercially reasonable interpretation, or in some cases declare a clause uncertain and unenforceable.

The outcome is rarely predictable, and almost never what either party intended.

The takeaway is simple: every dollar invested in a clear, well-drafted scope of works is a dollar that can save substantial legal costs down the line.

In commercial construction, the question isn’t whether your contract will ever be tested. It’s when.

The Real Cost Is Paid Long Before the Dispute

The contract mistakes that blow up construction projects aren’t complex or obscure. They’re the same drafting failures, repeated across the industry, because the scope of works is treated as a formality rather than the legal foundation it actually is.

Carlyon Ward has seen how quickly a vague phrase, a missing mechanism, or an unexamined damages clause can unravel a project that had every reason to succeed.

The fix isn’t complicated. It’s getting proper legal attention on the right document, at the right time before work begins.

Contractors who get the contract right protect their margins. Principals who get it right protect their delivery dates. Both avoid the legal costs that quietly outpace the savings of cutting corners at the drafting stage.

In construction, prevention is always cheaper than litigation and it’s decided long before the first invoice is issued.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.