Canberra light rail misses milestone targets by months

The consortium building Canberra's billion-dollar light-rail project has failed to meet all but one of its delivery targets this year.

The ACT Government has been forced to push back completion dates in five areas, including the laying of track and construction of the stops at each end of the line.

"Dynamic testing", which was supposed to begin in February, only started this month.

Four indicators set for completion by the end of the financial year remain unfinished, including the construction of a maintenance and control centre.

That building was slated for completion in March, but its revised target date has blown out five months, to August.

The only target the consortium was able to meet was the arrival of the first light-rail vehicle, which was constructed by Spanish firm CAF and shipped over in December last year.

Despite the delays, a spokesman for Transport Minister Meegan Fitzharris said the project was still on track to begin operation this year.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.