Big Ben repairs over budget by nearly £19 million

An extra £18.6 million is needed to repair the tower which houses Big Ben, parliamentary authorities have been told.

The new costs would see the renovation bill rise by almost a third from £61.1 million to £79.7 million.

The increase has been put down to the discovery of asbestos, pollution and the discovery of extensive Second World War bomb damage in the Elizabeth Tower, which is home to the capital’s famous bell.

But a spokesman for the House of Commons Commission said members were “extremely disappointed” by the request for “yet more funding”.

“It is very frustrating to learn that the Elizabeth Tower project requires yet more funding, having agreed an extra £32 million in 2017,” he said.

“We have requested more detailed information about the lessons learned from this experience – as well as assurances that more robust estimates are prepared for works of this nature in the future.”

The full scale of the work needed to complete the refurbishment by the late 2021 deadline only became clear when the renovation team began the first ever “intrusive surveys” on the 177-year-old structure, officials said.

The discoveries included asbestos in the belfry, broken glass in the clock dials, extensive use of toxic lead paint and defects in previous work, the House of Commons and House of Lords Commissions were told.

Ian Ailles, director general of the House of Commons, said the works are proving “more complex than we could have anticipated”.

“With a 12m square (130 square feet) footprint and a prime location right in the middle of a busy working Parliament, understanding the full extent of the damage to the Tower was impossible until the scaffolding was up,” he said.

“Alongside other issues, such as the impact of often inappropriate conservation methods used by our predecessors, the corrosive levels of pollution in the atmosphere and the discovery of asbestos in unexpected places, we have only now been able to fully understand the full investment required for this project.”

The new budget will be set if it is approved by the accounting officers of the two houses.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.