BHP second quarter iron ore output down nine percent, flags $600 million negative impact

FILE PHOTO: A BHP Billiton sign is visible behind a pile of iron ore at the company's loading facility in Port Hedland, Australia, May 30, 2008. REUTERS/Tim Wimborne/File Photo

MELBOURNE (Reuters) - Global miner BHP Group <BHP.AX> <BHPB.L> said on Tuesday its second-quarter iron ore production fell 9 percent and flagged a $600 million negative impact due to production disruptions at its copper and iron ore operations.

The world's biggest miner said unplanned production outages at Olympic Dam, Spence and Western Australia Iron Ore are likely to negatively impact productivity and flagged that it would revise guidance at its results on Feb 19.

The miner also raised its 2019 copper production forecast to between about 1.6 million tonne and 1.7 million tonne bolstered by the retention of Cerro Colorado copper mine in Chile, after a sale to private equity house EMR Capital fell through.

"Yes, iron ore output might have been a little softer but overall I'd say production was broadly in line," said a fund manager in Melbourne who declined to be named.

"I'd think about the $600 million as more of an opportunity cost that we knew about from earlier in the quarter."

BHP's iron ore output declined to 66 million tonnes during the three months ended Dec. 31, compared with 72 million tonnes a year ago, hurt by a forced train derailment that caused a supply disruption.

The mining giant had said in November that it expected some interruption to its Australian iron ore exports after it was forced to derail a cargo train loaded with the commodity after it ran away en route to a key shipping hub.

The Anglo-Australian miner has so far maintained its fiscal 2019 guidance of 273-283 million tonne of iron ore from its Western Australian operations.

In other metals, BHP's copper output fell 3 percent at 416,000 tonnes in the quarter, hurt by planned maintenance as well as outages.

BHP also flagged a $700 million first-half impact due to higher Australian and Chilean income tax payments than last year, and the settlement of an Australian transfer pricing dispute.

The state of Western Australia said on Monday that it was in talks with the miner after an audit had found that BHP had underpaid royalties on iron ore shipments sold via its Singapore marketing hub stretching back over more than a decade.

(Reporting by Rushil Dutta and Aditya Soni in Bengaluru and Melanie Burton in Melbourne; Editing by Sandra Maler)

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.