Get all your news in one place.
100's of premium titles.
One app.
Start reading
The Hindu
The Hindu
National
PTI

As many as 412 infra projects show cost overruns of ₹4.77 lakh crore in August: Report

As many as 412 infrastructure projects, each entailing an investment of ₹150 crore or more, have been hit by cost overruns of more than ₹4.77 lakh crore in August this year, an official report said.

According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects worth ₹150 crore and above, out of 1,762 projects, 412 reported cost overruns and as many as 830 projects were delayed.

"The total original cost of implementation of the 1,762 projects was ₹25,01,400.62 crore and their anticipated completion cost is likely to be ₹29,78,681.31 crore, which reflects overall cost overruns of ₹4,77,280.69 crore (19.08% of original cost)," the ministry's latest report for August 2023 said.

According to the report, the expenditure incurred on these projects till August 2023, is ₹15,57,188.10 crore, which is 52.28% of the anticipated cost of the projects.

However, it stated that the number of delayed projects decreased to 624, if delay is calculated on the basis of the latest schedule of completion.

Further, it stated that for 339 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Out of the 830 delayed projects, 194 have overall delays in the range of 1-12 months, 190 have been delayed for 13-24 months, 323 projects for 25-60 months and 123 projects have been delayed for more than 60 months.

The average time overrun in these 830 delayed projects is 36.96 months.

Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.

Delay in tie-up for project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, and law and order problems were among the other reasons.

The report also cited state-wise lockdowns due to COVID-19 (imposed in 2020 and 2021) as a reason for the delay in implementation of these projects.

It has also been observed that project executing agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are under-reported, it added.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.