384 infra projects showed cost overruns of ₹4.66 lakh crore in March quarter

As many as 384 infrastructure projects, each entailing an investment of ₹150 crore or more, have been hit by cost overruns of more than ₹4.66 lakh crore in January-March quarter, as per an official report.

According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects worth ₹150 crore and above, out of 1,566 projects, 384 reported cost overruns and as many as 931 projects were delayed.

Also read: 354 infra projects show cost overruns of ₹4.55 lakh crore

"Out of 1,566 projects, 384 projects were having the cost overruns of ₹4,66,874.46 crore which is 21.59% of their sanctioned cost," a quarterly report for January-March 2023 prepared by the ministry.

However, it stated that with regard to the latest approved cost, 285 projects had reported cost overruns of ₹1,97,069.19 crore. Further, it is noted that 259 projects are having both time and cost overruns.

The anticipated completion cost of these 1,566 projects is reported to be ₹26,29,193.77 crore.

The total expenditure as on March 31, 2023 was ₹14,71,873.93 crore which works out to 55.98% of the total anticipated completion cost and 68.06% of the original cost.

Also read: Road transport and highways sector has maximum number of delayed projects: Report

For these 1,566 projects, a total outlay of ₹2,81,251.99 crore has been allocated for 2022-23.

The Quarterly Project Implementation Status Report (QPISR) on Central Sector Projects (costing ₹150 crore and above) for the 4th quarter of 2022-23 (January-March 2023), contains detailed information on 1,566 projects covering 443 mega projects (each costing ₹1,000 crore and above) and 1,123 major projects (each costing ₹150 crore and above but below ₹1,000 crore).

Out of 1,566 projects, 12 projects were ahead of schedule, 292 projects were on schedule, 931 projects were delayed with respect to the original schedule of completion.

Further, it stated that for 331 projects, either original or the anticipated date of completion was not reported.

The percentage of delayed projects had changed from 41.27% in quarter ending March 2022 to 59.45% in quarter ending March 2023, it stated.

The percentage of cost overrun had changed from 21.43% in quarter ending March 2022 to 21.59% in quarter ending March 2023, it also stated.

The major factors responsible for time overruns as ported by project implementing agencies include environment, forest and wildlife clearances; land acquisition issues; state-wise lockdown due to COVID-19 (imposed in 2020 and 2021); contractual issues and shifting of utilities.

While the cost overruns due to general price escalation could not be avoided, the cost escalation on account of delay could be minimised, it suggested.

Sign up to read this article
Read news from 100's of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.